State-of-the-art compaction
technology is helping repair decades-old damage to the
Everglades.
The massive
population growth in South Florida during the past century has
significantly altered the Everglades environment. Wetlands were
drained to create dry land. Canals, roads, levees, and pumping
stations were built to provide flood control. Vast farmlands
added tons of pesticides to the runoff water with undesirable
results.
Today, in a more
enlightened time, more than $11 billion is being invested to
reverse this.
The massive
undertaking by the South Florida Water Management District is an
effort to significantly improve the quality of water in the
Everglades Protection Area. It is the largest project of its
type in the world.
The existing
SFWMD's Stormwater Treatment Area #2 is a 6,430-acre constructed
wetland treatment system located in southern Palm Beach County.
Presently it is divided into three cells which operate in
parallel. The original design of STA-2 was for receiving
agricultural runoff waters containing an estimated total
phosphate concentration of 50 parts per billion and, through
natural filtration flow through the cells in STA-2, reducing
phosphorus to no more than 20 ppb. The primary objective of the
ongoing STA 2/Cell 4 expansion project is to provide additional
treatment capability and further improve water quality.
This cell is a
submerged vegetation cell that contains a Naiad grass which
grows below the water's surface. The levees are all
approximately 14 feet wide at the top. The base level is about
73 feet across. The two levees under construction are about
12,500 feet long, and they turn north for about another 5,000
feet to tie into another supply canal levee.
The "seeds" for
the creation of the SFWMD were planted in the late 1940's by
flood and drought. Today, the agency's responsibilities include
regional flood control, water supply and water quality
protection as well as restoration of the ecosystem. With the
current environmental needs, the district instituted a new
program to accelerate the ecological remediation, and several
private sector contractors are being contracted to help with
this.
SFWMD
subcontracted engineering and geotechnical investigations to
Brown and Caldwell Engineering, and according to Project Manager
Don Stetter the contract (now called Acceler8) is being
completed on a fast track basis. Bergeron Land Development Inc.
is the earthwork subcontractor to The Gulf Group, the general
contractor on the $18-million Cell 4 expansion project. The job
involves handling a total of 1.2 million cubic yards of various
materials for construction of water retention levees, roads and
berms.
Because of the
extremely tight working deadline and the complexity of the soils
and rock being handled, Bergeron recently imported a new Bomag
BW225D-3 compactor outfitted with the Variocontrol (BVC) system
to help achieve thick lift compaction densities. The machine has
an operating weight of approximately 58,000 pounds, plus a
maximum centrifugal force of more than 90,000 pounds.
The first step in
building the new levees and canals is to clear that area of the
saturated ground level vegetation and muck. This is usually
dried and stockpiled for later reuse. A large tracked dozer
handles the task. The underlying limerock is then drilled and
blasted on a 15-foot by 16-foot square pattern. Damco drill rigs
were drilling 4.75-inch diameter holes 10 feet to 13 feet deep,
and on a typical day the two rigs were able to punch down an
average of 100 to 150 holes before blasting was done. Orica
Powernap powder was used for blasting. Fragmentation was good.
Large hydraulic
excavators then either sidecast or stockpile the crushed
material to drain and dry, or outload it into Terex TA30 end
dump haulers. The levees are built from the adjacent canal
material, which is stockpiled when not put on the levee
location.
The new Bomag
BW225D-3 has the ability to measure the compactive effort and
can chart (on a hard copy graph) progressively how the soil
tightens up. It gives the operator, by way of red or green
go/no-go indicator lights, a very good indication of where any
weak spots are and where more passes or density tests should be
made.
The Bomag
BW225D-3's Variocontrol single drum rollers, as being used by
Bergeron, incorporate an intelligent exciter system, which
enables the contractor to adopt an efficient and effective
on-site compaction management program. The new Terrameter BTM is
a support system for owners, engineers and roller operators. It
is used as an integrated working tool for continuous surface
area assessment of compaction and load bearing capacity of
granular soils, rock fills and unbound bearing courses. It
provides a direct test for soil densities during the compaction
process.
The Bomag
Terrameter relies on the relationship between the acceleration
of the vibrating drum and the dynamic stiffness of the soil to
measure compaction output. The measuring system monitors the
acceleration and indicates when optimum compaction has been
achieved, saving time and money.
Construction
manager Ed Bashman of Brown and Caldwell, which represents the
SFWMD, said that Bergeron Land Development requested permission
to put down the rocky levee building material in 36-inch thick
lifts instead of the previously specified thinner lifts.
"We took a look
at the request and agreed to do some studies including some
in-place testing," Bashman said, adding, "We decided to actually
go in and pothole down and test the density of the bottom 12
inches of the 36-inch lift."
At the same time,
he added, the test was for the possibility of rock nesting, a
situation where rocks cluster together and possibly form a flow
path through the material — something which would be
unacceptable.
"So far," he
said, "the geotechnical results have been very good. We have
noticed no signs of nesting, and the density readings using
Troxler nuclear testing equipment have all met the
specifications. Provided these results continue, we plan on
using the same testing procedures throughout the remainder of
this project."
If new approaches
and the use of new equipment capabilities make good sense from a
construction technology viewpoint, Stetter says, "We probably
will agree to take a look at it. If it proves out and will speed
the project along we will try to work with them to implement it.
That's simply taking advantage of today's changing technology."
Staff
February 05, 2007
Dixie Contractor
|