In southern Florida, an unusual
delivery system using two trailer-mounted pumps helps M&M
Concrete Pumping take on a challenging concrete pumping job in
an environmentally sensitive area.
Pumping concrete
for a 5-foot wide sidewalk may sound straightforward, but
accomplishing it in an environmentally protected area while
reaching the farthest point 1,644 feet away definitely presents
unique challenges.
To complete the
job, which was located within the 217-acre Yamato Scrub Natural
Area in Boca Raton, Fla., pumping contractor M&M Concrete
Pumping recently used two Putzmeister Thom-Katt trailer-mounted
concrete pumps. Used in an unusual pump-to-pump arrangement, the
Thom-Katts placed 80 cubic yards of concrete to construct the
long and curving sidewalk.
"The job was
brutal," says M&M owner Mike Moberg. "It's incredibly rare to
use two trailer pumps in a pump-to-pump approach, especially
when pumping a harsh 3/8-inch pea rock mix such an enormous
distance. Plus, we had to be extremely careful not to damage any
vegetation while pumping along a looping sidewalk path."
On a normal pour,
a trailer pump from M&M's 12-unit fleet uses about 200 feet of
delivery system. At eight times that distance, this job was an
exceptional and complex endeavor.
In addition,
keeping ready mix trucks from driving over and disrupting the
vegetation was key. Thus, the concrete (supplied by Maschmeyer
Concrete of Lake Park) was discharged at the scrub's edge, where
the first trailer pump, a model year 1998 TK 50, was positioned.
With its maximum 950-psi pressure, that unit pumped concrete 700
feet through 2-inch steel pipe and hose to a second pump, which
was set up on a narrow access road inaccessible to ready mix
trucks. That second high pressure unit, a bigger TK 70, pumped
the mix another 944 feet through larger 3-inch line that tapered
to a 2-1/2-inch size, while snaking around sharp bends before
reaching the furthest point of concrete placement 1,644 feet
away.
Delivery line
size proved to be a significant aspect of the complex pumping
equation.
"The smaller the
line size, the higher the pressure needed," notes Jim Henegar,
co-owner of Miami-based Thomas Machinery, the Putzmeister
equipment dealer in the area. "As higher pressures force water
into the rock, the mix tends to dry out and makes pumping more
difficult at such far distances." He adds, "As the concrete
would already be stiff from going the long distance from the
first pump to the second, M&M's use of a larger line size for
the last 944-foot stretch was a key factor in effectively
pumping the concrete the final distance."
And all of this
had to be accomplished while protecting the environment.
"As the area was
environmentally protected, the plants could not be disrupted in
any manner," says Moberg. "We could have avoided about 250 feet
of delivery system if allowed to make a beeline straight through
the scrub."
To address these
concerns, the delivery system had to remain within the curving
sidewalk forms. In addition, crews could only venture 18 inches
outside the forms on either side, paying special attention to
ensure no foliage was harmed during the construction.
There were also
environmental concerns with priming the pump with grout. As a
grout primer was a critical aspect, two yards of a high strength
6,500-psi mix were eventually proposed and allowed. To dispose
of the primer without placing it within the scrub's natural
habitat or compromising the sidewalk's integrity, crews placed
the strong mix as a low 1-inch layer within the overall 5-inch
thick concrete walkway.
Constructed under
the direction of concrete contractor West Construction of Lake
Worth, Fla., the challenging sidewalk was just one portion of a
contracted construction project for various sidewalks, small
parking lots and informational kiosks for three different scrubs
within Palm Beach County. Ultimately, these construction feats
will enable visitors to more conveniently view the natural and
exotic plant species along with the protected wildlife of this
rare ecosystem.
Staff
February 19, 2007
Dixie Contractor
|