|
A major runway rehab project
has been in the spotlight at the Southwest Florida International
Airport.
Asphalt paving
jobs come in all shapes and sizes — but for sheer complexity,
tight specs and critical timing, it's hard to top an airport
paving job.
Just ask the
folks at Ajax Paving Industries in Fort Myers, Fla. Ajax Paving
recently served as the pavement rehab and asphalt paving
contractor on a major taxiway and runway rehab project at the
Southwest Florida International Airport in Fort Myers, Fla.,
known to frequent travelers as RSW.
The airport was
born in the early 1970s when it became clear that Page Field,
the airport then serving the Fort Myers area, was not going to
be able to handle new aircraft and the expected increase in
traffic. A site near Interstate 75 (which was then under
construction) was eventually chosen for a new airport. Ground
was broken in 1980, and the new airport — then known as
Southwest Florida Regional Airport — opened on May 13, 1983. In
1993 the airport was renamed the Southwest Florida International
Airport; that same year, the runway was lengthened to 12,000
feet. To meet increasing traffic demands, a new Midfield
Terminal Complex was opened in 2005. And in the future, as usage
continues to increase, plans call for a second runway to open in
2010.
But that second
runway is still several years down the road. Meanwhile, the
airport has been in upgrade mode ever since the new terminal
opened in 2005 — and part of that upgrading is the recent
rehabilitation of the facility's existing runway.
Conversion of
Taxiway A into a temporary runway was approved by the Federal
Aviation Administration and the Florida Department of
Transportation in 2004. Plans called for runway renovation to
take place following construction of the new terminal, since the
terminal project included construction of an additional taxiway
(Taxiway F) to serve the new terminal. That taxiway, located
south of the runway, has been in use since the new terminal
opened and served as the taxiway while runway rehab work was
going on.
Typically, the
average life of a runway is about 20 years before resurfacing is
required, and Southwest Florida International Airport's runway
had been in service for 23 years. But rehabbing the runway at a
single-runway international airport is no small task. Planners
benefited form the experiences of other airports (including
Memphis, Oakland and Atlanta) which had experience in converting
taxiways to temporary runways. Preliminary planning, design and
coordination with the FAA, FDOT, various airlines, the Port
Authority staff, and consultants required about four years.
The plan that
finally emerged allows for rehabbing the runway with a minimal
amount of disruption to airport operations. Owen-Ames-Kimball
Co. was named as the construction manager to oversee the overall
project, with Leo Smith as project manager.
Ajax Paving was
chosen to handle the asphalt work. Key Ajax personnel involved
with the project include Dennis Breuer, area manager; Mike Graf,
project manager; Jim Mann, project superintendent; and Robert
Peterson, paving superintendent.
The overall plan
called for first converting an adjacent taxiway (Taxiway A,
located on the north side of the existing runway) to a temporary
runway with a length of 10,000 feet and a width of 150 feet.
Following the conversion, landings and take-offs would be moved
to that temporary runway while rehab work on the existing runway
was completed.
The first step
was to convert Taxiway A into a temporary runway. That portion
of the work required not only widening the taxiway to 150 feet
but also leveling, resurfacing and cross-slope grade adjustment.
The 400-foot-long connectors on each end had to be milled,
leveled and paved as well; the connector work had to be
completed within a very short five-hour window. Various other
crossovers also had to be reconstructed.
The work began
with milling and was handled in thirds, starting on the west end
of the runway. Turtle Southeast, Tampa, worked as a
subcontractor to Ajax paving to handle the milling operation,
removing an average of 2.5 inches of material with some cuts
being as deep as 3 inches to 4 inches. These millings, as well
as all subsequent millings at the site, were recycled at Ajax
plants for use on other projects.
With milling
complete, Ajax crews then began placing new virgin asphalt atop
the milled surface. The first ton of mix was placed March 1,
2006, using a paving spread which included a Blaw Knox 3200
paving machine, a pair of Sakai 850 double-drum vibratory
rollers, a Bomag seven-tire rubber-tired roller, and a Hypac
steel drum finish roller. A Roadtec SB2500 Shuttle Buggy was
also utilized during much of the project. During paving, the
shuttle buggy was offset to keep asphalt trucks from running on
the tacked surface.
Besides providing
a smooth surface for take-offs and landings, a major goal of the
paving operation was to correct the cross slope from 1.5 percent
to 1 percent.
"That doesn't
sound like a lot until you take it across the entire 150-foot
width," notes Mann, adding that in some areas as many as seven
1.5-inch lifts were required to yield the desired surface.
The team utilized
Pavesmart technology to eliminate the need for staking and
string during the paving operation.
After a 30-day
cure period, Cardinal International Grooving took care of
grooving the 10,000-foot-long temporary runway. Working 24/7,
grooving required about seven days to complete.
The
taxiway-turned-runway was turned over to the airport on Sept.
16. Immediately, the numbers on the old runway were blacked out
and new markings were applied to the temporary runway to
eliminate any risk of confusion over the correct place to land.
Meanwhile,
electrical work was going on along the old runway — and as it
was completed, milling followed close behind.
During the runway
phase of the work, Ajax Paving utilized the same approach as
during the taxiway conversion. First, milling removed an average
of 2.5 inches of material. Then, as milling was completed, new
asphalt was placed using the Pavesmart system. Finally grooving
added the desired surface texture.
The first third
of the runway rehabilitation was completed by Christmas, with
rehab and repaving totally finished by late January.
Overall, about
100,000 tons of mix was required to complete this project. About
59,000 tons of mix was utilized during conversion of the taxiway
to a temporary runway; another 41,000 tons was required during
rehab of the old runway. The mix was manufactured in two Ajax
plants — the company's Cook-Brown Road Plant and also the plant
on Alico Road.
In addition to
the asphalt paving, a 3/8-inch-thick slurry seal surface
treatment was applied to the shoulders. Mixed on-site, the seal
was applied using a small paving machine.
Grooving of the
rehabilitated runway, with its length of 12,000 feet, took about
10 days.
As soon as runway
rehab paving was complete, attention turned immediately to
applying lettering and striping to the new runway while blacking
out the marking on the temporary runway in order to eliminate
any chance of pilot confusion. All agree that this short window
is one of the most critical parts of the project, as incoming
pilots are faced with two new-looking runways located side by
side. Thus, quick attention to pavement marking was critical.
It's no surprise
that a project such as this brings its own unique set of
challenges. As on many paving projects, traffic control was
certainly an issue — but the traffic in this case was airplanes,
not cars. The reason had to do with the layout of the site. The
original Taxiway A, which would become that temporary runway,
was located to the north of the existing runway (the one to be
refurbished). Taxiway F, the new taxiway which would remain in
service, was located to the south of the original runway. In
other words, once take-offs and landings were shifted to Taxiway
A to allow runway rehab to begin, every single commercial
aircraft using the airport would have to cross the old runway to
get from the terminal and Taxiway F to the temporary runway —
all while rehab construction was going on.
Another
challenge, particularly during the hotter seasons, was the
simple matter of heat.
"We completed the
Taxiway A conversion during the heat of summer," Breuer says,
"and on a runway like this there is no shade at all. There is
literally nowhere to go to get out of the sun, and the guys
working out there earned every penny they made."
By Steve Hudson
April 16, 2007
Dixie Contractor |