In Georgia's
Cherokee County, roller compacted concrete (RCC) has been in the
spotlight as construction moves ahead on the dam at the Hickory
Log Creek Water Supply reservoir.
Roller compacted
concrete, also known as RCC, has been in the spotlight in
Georgia's Cherokee County, where it was used to construct a
massive RCC dam at the Hickory Log Creek Water Supply reservoir
within the city limits of Canton, Ga.
Brown and
Caldwell, based in Atlanta, and Schnabel Engineering, based in
Alpharetta, Ga., handled overall design of the pump storage
augmented project. Schnabel's Randy Bass served as project
manager for the dam, assisted by on-site construction manager
Chuck Kahler.
The contract for
the first phase of the project — which included clearing,
excavation, foundation exploration and preparation, and related
work to ready the dam construction site for RCC placement — was
awarded to Thalle Construction, based in Hillsborough, N.C.
Thalle Construction is also the contractor on the current Phase
2, which includes construction of the actual RCC dam, with ASI
Constructors serving as the RCC placement subcontractor. The
overall project cost of more than $56 million is being shared
between the Cobb County-Marietta Water Authority and the city of
Canton. The project will help meet water needs for the city of
Canton and the authority's service area through 2050.
The Hickory Log
Creek dam has a design length of 980 feet and a height of 180
feet. Its width varies from 147.6 feet at the base to 18 feet at
the top. The completed structure, which will be the highest
non-federally regulated dam in the state of Georgia, will create
a 411-acre lake that will provide as much as 44 million gallons
of water per day. The lake's water will come from natural inflow
from Hickory Log Creek, augmented by a pumped-storage system
which will pull water from the nearby Etowah River when
conditions permit it.
Formwork
The dam is
designed with a flat, vertical upstream face and a stepped
downstream face. Its downstream steps were formed using wood
forms, creating steps with a height of 3 feet. On the upstream
side, the team used precast stay-in-place concrete form panels —
typically measuring 16 feet by 6 feet 6 inches with a thickness
of 5 inches — to define the face of the dam. The inside face of
each of these panels is lined with an impervious geomembrane.
Crews fabricated and cast these panels at an on-site precast
yard.
To anchor these
upstream forms during RCC placement and compaction, permanent
anchors extending back into the RCC were attached to the inside
face of each form panel. Additionally, temporary exterior steel
stiffbacks were installed to provide additional support.
Overall, the design utilizes close to 1,100 of the panels.
Not all formwork
was on the outside of the dam. The Hickory Log Creek dam
includes an inspection/drainage gallery which has been
constructed deep within the dam itself. This gallery has a width
of 7 feet and a height of 8 feet. The walls were formed during
RCC placement using removable metal forms; gallery ceiling was
constructed using precast reinforced concrete roof panels.
Access stairways have also been incorporated into the mass
structure. The presence of these openings and passages
complicated construction somewhat but allows for easy
instrumentation, drainage from the foundation drains and
interior inspection of the structure.
RCC Production
And Placement
Overall, the
dam's design calls for the use of about 225,000 cubic yards of
RCC. ASI Constructors produced the RCC on-site in a Johnson-Ross
batch plant, utilizing aggregate from the nearby Lafarge quarry
in Ballground, Ga., and cement from Signal Mountain Cement Co.
Fly ash was also utilized in the mix design. The six-yard plant
typically produced about 350 yards of RCC per hour.
The mix was
delivered to the dam via a conveyor system manufactured,
installed and maintained by Rotec Industries. An initial
conveyor run of about 700 feet carried the mix from the plant up
the hill to a transfer station; from there, a second conveyor
transported the mix along the top of the dam to a "tripper." The
tripper, which could be positioned along the second conveyor's
run, diverted the RCC from the distribution conveyor and
discharged it onto the working surface at the desired location.
As the RCC was
discharged by the tripper, it was spread in 12-inch lifts by a
dozer. Initially, during placement of the first lifts of RCC, a
small Komatsu D21A dozer was used for maximum maneuverability.
Then, as RCC placement continued and placement rates increased,
the team switched to a larger Caterpillar D5MXL and then to an
even larger Deere 850 dozer outfitted with wings on the blade.
Toward the top of the dam, as the working area began to narrow,
the Cat D5MXL was again called into service.
As the dam's
elevation increased, the columns supporting the second stage of
the conveyor system were raised using hydraulic jacks.
Typically, the conveyor was raised about every two days. As the
support columns were jacked up, they left behind openings in the
RCC which provide drainage or ventilation to the gallery.
After being
spread by the dozer, the RCC was compacted by a pair of
Ingersoll Rand rollers — a DD125 and, for working close to the
edge forms, a DD24. Additionally, vibratory plate compactors
were used to compact the mix near the edge forms and around
various penetrations.
On the downstream
side of the dam, the RCC face will be visible. To enhance the
appearance of those faces, the construction team utilized
so-called grout-enriched RCC to yield a smoother face. This
involved placing uncompacted RCC along the form edges, applying
a neat cement grout onto the RCC surface, then vibrating the
grout into the RCC to enhance a narrow zone of RCC and thus
yield a smooth formed face. Komatsu and Deere loaders were used
to transport the facing concrete from ready mix trucks to the
locations where it was used.
Temperature Issues
Temperature is a
concern during any RCC project, particularly one such as this
where such a large volume of RCC is being placed. RCC produces
heat as it hydrates and cures, and that heat can cause cracking
if it is excessive.
To avoid
overheating problems, RCC placement was scheduled to avoid the
heat of day. Placement typically began at about 5 p.m. and
continued through the night, wrapping up mid-morning before
temperatures got too high.
Temperature
management was further aided by the fact that most of the
aggregate was stockpiled last winter, during cold weather. The
core of the aggregate pile remained cool even as the weather
warmed — an additional aid in controlling mix temperature.
Should ambient temperatures have risen too much, the team had
the ability to add liquid nitrogen to the mix to lower the
temperature further.
Temperature was
also a major factor in determining whether bedding mortar was
used between each placement session. Although bedding mortar was
used in a narrow zone on the upstream side and at each abutment
contact at the beginning of each day's RCC placement, it was
only necessary to bed the entire lift if the "degree-hours"
(that is, the product of the temperature and time between lifts)
exceeded 500 degree hours.
Multiple Cranes
Because of the
location and layout of the site, a key factor in maintaining
production was ensuring that materials and equipment could be
delivered to the dam construction crew where and when they were
needed.
To that end, ASI
utilized four large cranes on the project — a Kobelco 100-ton
crane on one end of the dam, a Liebherr 120-ton crane on the
other end, a Manitowoc 4100 on the downstream side, and a
Manitowoc 888 on the upstream side — as well as smaller cranes
and lifts elsewhere as needed. Having multiple cranes on-site
allowed maximum lifting flexibility at any point on the dam.
Other Project Elements
Besides the RCC
work, Phase 2 work at the Hickory Lock Creek project also
includes significant conventional concrete work. Thalle
Construction's crews handled this portion of the work, which
includes construction of the dam's conventional concrete crest —
which measures a foot thick and is 700 feet long — as well as
construction of the overflow section of the spillway, the
spillway training walls and the stilling basin at the bottom of
the spillway.
Thalle's work
also included additional site work in the abutment areas,
handled after RCC placement was complete.
As work on the
dam itself continues, subcontractor West Contracting, based in
Marble, N.C., has been working to clear the actual reservoir
area.
RCC placement was
completed in early June. Additional work on the dam will
continue over the next few months, with filling of the reservoir
beginning this fall.
By Steve Hudson
June 18, 2007
Dixie Contractor |