A fleet of
excavators, loaders, dozers, and other machines — combined with
careful attention to client needs — helps Forsberg Construction
dig into underground utility and site development work in
southwest Florida.
Utility and site
development construction continues to do well in southwestern
Florida, and one company active in that market is Forsberg
Construction.
Forsberg
Construction, formerly known as T.A. Forsberg, Inc. of Florida,
has been handling a variety of municipal and private projects in
Southwest Florida since 1982. Growing out of T.A. Forsberg
Incorporated, Okemos, Mich., the company got its start when
Terry Forsberg, Richard L. Wendorf, and two other partners
looked south and formed T.A. Forsberg, Inc. of Florida.
T.A. Forsberg,
Inc. of Florida was incorporated in Florida in September of 1982
following the completion of the Deep Creek Development in Port
Charlotte, Fla., a $21-million joint venture with Eisenhour
Construction. Richard Wendorf, an employee with T.A. Forsberg
Inc. since 1957, served as president of the company from March
1990 until Dec. 31, 2005, and became the sole owner of the
company in August 1997. Currently, Bruce Wendorf, Richard's son,
serves as president, with Gregg Marsh as vice president.
These days,
Forsberg Construction, handles projects ranging from public
utility systems and rural and urban roadways to site development
for golf courses, subdivisions, colleges, churches, and retail
shopping centers. The company focuses on southwestern Florida,
primarily in Manatee, Charlotte, Lee, Hendry, Desoto, Collier,
and Sarasota counties. Bruce Wendorf notes that over the years
the company has developed into a complete sitework contractor,
handling not only pipe work and underground construction but
also excavation, grading and road construction.
"We do everything
but the paving and curbing," he says, adding that the company's
projects range from golf course communities to large commercial
jobs to work for public and private utilities.
Municipal
Water And Sewer Upgrades
One of Forsberg
Construction's recent jobs, a major utility upgrade for the city
of Cape Coral, fell into that latter category. MWH Constructors,
Cape Coral, Fla., is serving as construction manager on the
overall project — a multi-phased effort to get local homes and
businesses off of septic tanks and water wells and onto gravity
sewer and a municipal water supply, while also supplying
residents with irrigation water and upgrading existing
underground stormwater infrastructure to current standards.
Each phase of the
project is completed under multiple contracts, with individual
contracts typically ranging from $5 million to about $15
million. Forsberg Construction is one of the contractors active
in the upgrade program, with Andrew Hume as superintendent,
assisted by foremen Luis Aparicio, Dean Campbell, Doug Adcock,
Evert Warren, and Joe Knapps.
On one recent
contract, Forsberg Construction's work included construction of
about 40,000 feet of 8-inch gravity sewer, installation of
34,500 feet of 8-inch and 6-inch water line, and installation of
44,000 feet of irrigation pipe in diameters of 4 inches, 6
inches, 8 inches, 12 inches, and 24 inches. Though irrigation
and water lines were relatively shallow and run down the sides
of local roads, installation of the new gravity sewer required
cuts to depths approaching 20 feet in some areas. And — because
new gravity sewer runs down the middle of the existing streets —
the project also includes road work needed to remove and
reconstruct the local streets and four-lane boulevards.
Work was
completed in sections of about 3,000 feet each and began with
milling of the existing roadway. Subcontractor PMI, based in
Fort Myers, milled and mixed the existing asphalt pavement and
base in place. The resulting material was then treated as virgin
ground.
Underground
construction began with sewer line installations. On this
particular project, there were existing lift stations; so the
new sewer lines tied into existing manholes.
"And once tied
in," Wendorf says, "we just took off."
As a section of
underground work was completed, attention turned to base and
paving on that section of the new asphalt street. New limerock
base was compacted by a Bomag roller, readying the site for Ajax
Paving to place new asphalt pavement.
Multiple Excavators
Much of the
excavation was in sand, but throughout the area crews had to
deal with a 1-foot-thick to 3-foot-thick layer of rock
encountered at a depth of 2 feet to 9 feet. Because of the
highly varied nature of the work, a number of different
excavators have been utilized on the project.
Equipment used
included several Komatsu excavators, including a large Komatsu
600 outfitted with a heavy-duty excavation bucket. Also busy on
the project was a Komatsu 300 outfitted with a breaker
attachment. No blasting was allowed, and no rock trenching was
required.
Elsewhere on the
project, smaller excavators stayed busy. For example, Komatsu
PC78US excavators — outfitted with a 60-inch ditching bucket and
using polycarbonate shoes — handled installation of smaller
service lines. With their polycarbonate tracks, these machines
were also able to work from freshly paved road surfaces to
handle assignments such as driveway removal, grading and
restoring lawn edges.
Dealing With Rock
Rock figured into
much of the project, whether when used as bedding material or
when encountered during excavation.
Number 57 stone
was used as pipe bedding for the sewer lines, while number 89
stone was used to bed the pressure pipe. Stone came from local
sources.
The biggest
rock-type challenge, however, stemmed from that widespread rock
layer. What became of that excavated rocky material? It was
transported by Volvo off-road trucks to a central processing
area, where it was screened to produce clean backfill material.
At the screening site, a Cat 966 loader handled material and
loaded processed backfill material back onto the trucks. The end
product was clean backfill for the ongoing sewer line
installation.
"In essence," he
says, "we were reusing all backfill material during construction
of the new lines."
Back on the site,
a Komatsu 380 loader was among the machines placing the
processed fill and carrying stone bedding material to the pipe
crews. Several Cat dozers also worked on trench backfilling. A
Bomag vibratory roller compacted the sewer trench backfill
material.
Making Equipment
Choices
When selecting
machines for his fleet, Wendorf says that he "likes to have a
mix of manufacturers" but adds that he tends to standardize
within types of equipment. For instance, many of the company's
excavators are Komatsu. Similarly, his dozers tend to be
Caterpillar. According to Wendorf, focusing on a single brand
within a given equipment category allows for commonality of
buckets, filters and so on, allowing interchangeability and
simplifying maintenance.
Since maximizing
productivity is always a concern, Wendorf adds, he also
considers speed. But he adds that numerous on-site factors are
equally significant determiners of productivity and can diminish
the importance of speed alone.
"These include
the presence of existing utilities, the water table and other
such variables," he says.
"One of the most
important things in choosing equipment," he continues, "is the
level of service that the local dealer can provide." He says
that dealer service is "at least half" of what he considers in
selecting the equipment he uses on his jobs.
Wendorf adds that
the combination of sandy soil and a layer of rock can be hard on
equipment. To keep his machines in top condition, he continues,
Forsberg Construction maintains its own shop, staffed by a shop
manager and two mechanics. The company also fields its own
service vehicles to make equipment repairs on-site.
Communication Is Key
Because of the
diversity of projects such as this one, which involves multiple
contractors working in multiple areas at the same time, great
attention is given to coordination among the many parties
involved. The construction manager meets with the various
contractors involved at least once a week, alternating between
field meetings and meetings in the office. This assures that
coordination of efforts is always addressed in a proactive
manner.
Another important
aspect of such work has to do with interfacing with residents
and businesses in the areas where the work is going on.
Particularly on residential projects such as this one, Forsberg
notes, close communication with those who live and work in the
project area is another key to project success.
"We are
constantly in contact with the area residents to ensure their
individual needs are being addressed to their satisfaction," he
says.
Staff
February 05, 2007
Dixie Contractor
|